Ghana’s efforts to decommission the Saltpond Oil Field have hit a snag, with concerns mounting over the project’s management and accountability. The offshore site, which generated a modest $10 million in revenue over five decades, is now facing a whopping $200 million cleanup bill.

Saltpond Oil Field

Initial estimates had placed the decommissioning cost at $100 million, but the latest projections have sparked alarm. Bright Simons, Vice President of IMANI Ghana, took to Twitter to reveal that nearly half of the projected budget has already been spent, with little progress to show.

The controversy has put the spotlight on Hans & Co, the contractor handling the decommissioning project. Questions are being raised about the company’s competence and the government’s oversight of the project. As the costs continue to escalate, Ghanaians are demanding answers about the management of the project and the value for money. The government is under pressure to provide transparency and accountability in the handling of the decommissioning project.

Ruth Abla ADJORLOLO