The Select Committee on Roads and Transport conducted a working visit to the Boankra Integrated Logistics Terminal (BILT) in the Ashanti Region to oversee the project’s progress. Led by Chairman Kennedy Osei Nyarko, the committee aimed to gather firsthand information from stakeholders, including the contractor, consultant, Ghana Shippers Authority, and Ministry of Roads and Transportation.
Project Director Dr. J.B. Koranteng-Yorke briefed the committee on the project’s background and status, highlighting its potential to handle imports and exports from the Northern regions and neighboring countries.
The committee expressed concerns about the project’s pace and urged the government to settle the contractor’s outstanding payments, totaling several millions, since November 2023.
Chief Director of the Ministry of Transport, Mabel Sagoe, explained the termination of Ashanti Port Services’ contract due to financial commitment breaches. She agreed to submit relevant documents to the committee for review. The project, now handled by Justmoh Construction, is approximately 40% complete.
The committee emphasized the project’s significance and pressed for prompt payment to ensure its timely completion by 2026. Managing Director of Justmoh, Mr. Justice Amoh, assured the committee of the company’s commitment to meeting the scheduled deadline.
Ruth Abla ADJORLOLO